Çöpler Gold Mine

Transkript

Çöpler Gold Mine
August 2012
Agenda
Lidya Mining
Çöpler Gold Mine
Çöpler Sulfide Project
New JVs
Gold Market
2
Agenda
Lidya Mining
Çöpler Gold Mine
Çöpler Sulfide Project
New JVs
Gold Market
3
Lidya Mining
 Lidya established in 2006, based in Istanbul, fully owned
by Çalık Holding.
 Focused on metals and precious metals in and around
Turkey.
 People, assets and partnerships; 3 pillars of strategy
 An emerging mining company through Çöpler experience
and cashflow
 Committed to create a valuable portfolio of gold, copper,
molybdenum, and nickel.
4
Mission & Vision & Values
 We are committed to create value for our shareholders,
Mission
Vision
Values
employees and social partners through discovery, acquisition
and development of high quality metal assets and operation of
profitable mines.
 We will be the most valuable and respected mining company in
Eurasia.
Sustainable and Socially Responsible Development
 Win-Win Relationship with Communities and Partners
 Integrity
 Overriding Commitment to Safety and Environment
 Fostering Team-Spirit in the Pursuit of Excellence
5
Agenda
Lidya Mining
Çöpler Gold Mine
Çöpler Sulfide Project
New JVs
Gold Market
6
Çöpler Gold Mine
Çöpler
Gold Mine
7
Çöpler Gold Mine
 Çalık&Alacer Gold (TSX:ASR) joined forces in August 2009 is the first
major international partnership in Turkish mining industry
 First operation is a gold project in eastern Turkey, Erzincan
 Çöpler is the second biggest gold mines in Turkey with 7.3Mozs resources
(inclusive of reserves)
Çöpler sits on a comfortable margin with a cash cost of US$350
Open Pit
Leach Pad
8
Çöpler Gold Mine
Çöpler New Gold-Copper District
YAKUPLU
BAHÇE
SABIRLI
BAYRAMDERE
AKSEKİ
DEMİRMAĞARA
Au-Cu prospect in-line
with major Çöpler
structure
Çöpler
+7.3Moz Au deposit,
closed only to
immediate east
Multiple Cu-Au
prospects along 6km
contact zone
FIDIKLIDERE
Karakartal
Target large Au-Cu
porphyry.
3 rigs 2H11 following up
235m at 1.0g/t Au,
0.43% Cu
9
Past, Present, Future...
Çalık & ASR
strategic
partnership
1930
5/2006
Çalık
Mining
established
8/2009
Sulfide
feasibility
starts
1994
12/2010
First gold at Çöpler
6/2011
9/2011
New JVs into
16 projects
10/2011
Çöpler
produces
400K ozs Au
Sulfide
feasibility
completed
First drilling
in 50/50 JVs
1/2012
Shares in
Anagold raised
to 20%
2007
12/2012
2008
1/2013
1/2015
Sulfide
construction
starts
10
Çöpler Gold Mine
Investment
Employment
Reserve
Cash Cost
• $250M
• 700 employees
(255 from Ilic and around)
• 4.6 Mozs (≈130t)
• 350 $/oz
2011 Production • 185.417 ozs (≈5,3t)
2011 Turnover
• $288M
2012 Production
• 200.000 ozs (≈5,7t)
(estimated)
11
Çöpler Gold Mine
Exploration Investment
$30M
Completed Total Drilling in meters
188.083m
Completed Total Drilling in Holes
1.250 holes
Total Capital Investment (1,3Mozs oxide ore)
$220M
2012 Drilling Works
Budget
Planned
Completed (YTD)
$10M
48.000m
33.112m
12
Çöpler Gold Mine
Production by Years
13
Çöpler Gold Mine
Open Pit
Crusher Plant
Manganese Zone
ADR Plant
14
Agenda
Lidya Mining
Çöpler Gold Mine
Çöpler Sulfide Project
New JVs
Gold Market
15
Çöpler Sulfide Project
Probable
Reserves
2.2Mozs
4.6Mozs
LOM
Production
1.3Mozs
3.7Mozs
Mine
Life
9 Years
16 Years
Facility construction starts; 2013
Facility construction period; 28 months
Full capacity production; 2015
Additional production per year; 220.000 oz
16
Çöpler Sulfide Project
$410M
• CAPEX
$739M
• Net Cash Flow *
430 $/oz
24,6 %
• Cash Cost
• IRR
•Accepted Au price 1.035 $/oz
•Based on prefeasibility report
17
Agenda
Lidya Mining
Çöpler Gold Mine
Çöpler Sulfide Project
New JVs
Gold Market
18
New JVs
19
New JVs
Çöpler
PRODUCTION
Oxide
Çöpler Sulfide
FEASIBILITY
Cevizlidere, Karakartal
Fındıklıdere, Bayramdere
Polimetal:
Akoluk, Balışeyh, Dursunbey, Eğrikar,
Güvemli, Fol-Ken, Ken-Fol, Kabadüz,
Kurttepe, İvrindi, Yelekkaya,
Taşlıkyayla, Sarıçayıryayla, Şiran
ADVANCED
EXPLORATION
INITIAL
EXPLORATION
20
New JVs
KARAKARTAL EXPLORATION
Properties
Location:
12km southeast of Çöpler
Primary Target: Porphyry Cu-Au
Ownership:
50% Lidya Mining
Drilling Works
Previous terms
9.541 m
2011 Completed
4.301 m
2012 Completed (YTD)
5.848 m
21
Agenda
Lidya Mining
Çöpler Gold Mine
Çöpler Sulfide Project
New JVs
Gold Market
22
Gold Market
* Estimated
Source: Assosiation of Gold Miners
23
Top Gold Producers of Turkey
2011 Production
Anagold
25%
Tüprag
38%
2012 Estimate
Anagold
21%
Koza
37%
Koza
37%
2011
Tüprag
42%
2012
24
Gold Market
25
Thank You